This table shows some typical monitoring methods for the example provided earlier. Note that you should re-state the specific control measure you've chosen for this part of the assignment.
Title of document | Description | Purpose in the monitoring process |
---|---|---|
Follow-up risk assessment. | New risk assessment carried out after the steel handrail and gate have been installed. | To determine the risk rating once the control has been implemented and to check that no new risks have been introduced. |
Gantry crane pre-start checks. | Pre-start checklist completed before the gantry crane is used each day. | To make sure that the crane operator is completing all the required checks before opening the gate to receive loads. |
Toolbox minutes. | Minutes taken of meetings conducted after the new system is in operation. | To see whether any issues have been raised by workers in relation to the new handrail and gate. |
Safety committee minutes. | Minutes taken of meetings conducted after the new system is in operation. | To see whether the safety reps have raised any new issues. |
Job title | Role in relation to control | Questions to ask |
---|---|---|
Gantry crane operator. | Operator who opens the gate and directs others in the area while loads are being received. | Is the new handrail and gate system structurally sound and working properly? Are the other workers staying clear of the area while the gate is open? Is the gate being closed immediately after the load has been received on the first floor? Is it slowing down your work or causing any other production problems? Has it introduced any new hazards? |
Area supervisor. | Person in charge of that section. | Same questions as above. |
Description of action or observation | Purpose |
---|---|
Watch the lifting operation the first time the gantry crane is used with this new system. | To see whether the safe operating procedure (SOP) is efficient and appropriate for the job. To check that the gantry crane operator understands what to do. To check that other workers in the area understand what to do. |
Watch the lifting operation one week later. | To check that the SOP is still being followed properly by all personnel. To see whether the SOP needs fine-tuning. |